Severity vs priority — with an example.

Show answer
Severity = impact on the system. Priority = urgency to fix. Logo misspelt on the homepage → low severity, high priority. Crash in a rarely used report → high severity, low priority.
05

A bug is not reproducible. What next?

Show answer
Re-check environment, data, browser and steps; check the logs; try the reporter's setup; add video and console logs; mark it 'cannot reproduce' only after discussing with the developer, and keep monitoring.